Broadway Bridge Painting
DESCRIPTION
As a subconsultant, Emerio provided temporary traffic control plans for this bridge closure due to needed deck repairs and painting. The painting schedule was 70 days, making traffic flows and changing patterns for each section of the work a critical component of the project. Traffic flow was merged into two lanes during the painting project. Close coordination was required with PBOT to place signs along travel corridors east and west of the river, and ODOT as well, since signage was required on I-5 ramps.